RecommendedSafetyPrecautionaryMeasures
andWorkProceduresforWorkinginLiftShaft升降机槽工程的建议安全预防措施及施工程序
;
(A)Safetyproblemsonliftshaftworks升降机槽工程之安全问题
(B)Extentandscopeofliftshaftworks升降机槽工程之涵盖范围
(C)KeypointsoftheCICnewlypublishedGuidelinesonSafetyofLiftShaftWorks(Volume1):
建造业议会新发布之升降机槽工程安全指引(第1卷)的要点︰lPlanningofliftshaftworksandtheprovisionofprotective
measures
升降机槽工程之规划及保护措施
lRiskAssessment风险评估
lImplementationofaPermit-to-WorkSystem工作许可证制度之实施
(D)Summary总结
E)Enquiries查询;
(A)Safetyproblemsonliftshaftworks升降机槽工程之安全问题;
lduringconstruction,liftinstallation,operationandmaintenancestages,manyactivitiestakeplaceinsideornearliftshafts
在施工、升降机安装及操作和保养阶段,均有大量工作于机槽内部或附近进行
laccidentsinliftshaftcanbecatastrophiccausingseriousinjuriesorevenlossoflivesanddamagetoproperties
涉及升降机槽的意外可以引致灾难性的后果,导致受伤、生命及财产的重大损失
lurgentlyneedtoenhancethemeasuresforsitesafetyofworkinginliftshaft
有必要加强在升降机槽工作的工地安全措施;
-theTaskForcewasformedundertheCommitteeonConstructionSiteSafetyoftheCIC
建造业议会(议会)辖下的工地安全委员会特别成立了专责小组
-membersoftheTaskForceinclude
professionalsandsafetyspecialists
小组成员包括建造业的专业人士及安
全专家
-aimatformulatingmeasuresto
enhancesitesafetyofworkinginliftshaft
目标为制订良好守则,以提升在升降机槽工作的工地安全;
Afterthoroughlyreviewedtheworkcycleinvolvingtheinstallationofliftswithinaconstructionproject,the
wholeprocesscangenerallybedividedintothreestages:
经全面检讨升降机安装的工作周期后,归纳为以下三个工程阶段:
lStage1–DuringConstructionStageandBeforeHandingOvertoLiftInstallationContractor
第一阶段-施工期间直至移交予升降机安装承建商前;;
(B)Extentandscopeofliftshaftwo