METHODSTATEMENT

FORSOILCEMETNWALL

(YANGONINNOCITYDEVELOPMENTPROJECT)

Sep2017

Contents

TOC\o1-2\u1.SOILCEMENTWALL 1

1.1Summary 1

1.2.Mobilization 2

1.3MaterialSupplyAndMethodOfTransportAndStorage 5

1.4SCMWork 6

1.5QA/QC 12

1.6.TestImplementation 13

1.7.OrganizationOfProjectTeam 15

1.8.HESManagementPlan 16

1.SOILCEMENTWALL

1.1Summary

1.1.1.SoilCementWall(SCM)methodistheprocessofimprovingpropertiesofexistingsoils,whichareessentiallysoftclay,bymixingstabilizingmaterial,cement,withexistingsoils.

1.1.2.Soilcementwallscanbeinstalledbymechanicalmixingmethodbymeansofwetmixing(slurrytype).Themixingofstabilizingmaterialtotheexistingsoilsatvariouslevelsshallcreatesoilcolumnswithapredeterminedstrength,depthanddiameter.

1.1.3.QuantityofWorks

ExtensionLength:750m(asshowninfigure1.1)

HoleQuantity:751nos

HoleDiameter:D1300mm,C.T.C1,000mm

Depth:11.5~18.6m

TotalHoleLength:13,435.75m

Figure1.1SCMArea

1.2.Mobilization

1.2.1.Equipment

JUZ180-2willbeusedtosoilcementwallconstruction.JUZ180-2is2axistwinaugermixingpilemachine.Themachinespecificationisshownasfollows.

Figure1.2SCMMachine

Figure1.3SCMRig

Figure1.4CementSlurryPlantandSCMRigs

Table1.12Axistwinaugerspecification

NO.

NAME

QTY

SPECIFICATION

1

2Axistwinauger

1ST

(110kw*8p*380V*2ST)20RPM

2

Controlpanel

2ST

(110KW*8P*380V)

3

Cable

2ST

(95SQ*3C*40M)

4

Cable

1ST

(125SQ*3C*6M)

5

R-rod

6ST

(Φ267*21.4T*120M*6M)

6

R-rod

2ST

(Φ267*21.4T*120M*3M)

7

Mixingbit

4ST

(Φ1300*Φ267*120M*4M)

8

MixingBand

4ST

(Φ267*C/L1000*2TWIN)

9

BUSING

8ST

(Φ270*325)(SHEEL)

TheplantsforSCWarelistedbelowinTable1.2.

Table1.2Equipmentlists

NO.

EQUIPMENTNAME

PARAMETER/

CAPACITY

QUANTITY

PRODUCTION

1

Basemachine(JZU180)

20×7m

1

China

2

Auger(SW300)

2×110kW

1

Korea

3

Shaft(GH1300)

2×Φ1300

1

China

4

Mixingsystem

(JBZ-60)

mixingdrum

30kW,2.5m3/drump

1

C