谈污水排海管项目施工阶段管控要点
TalkingAbouttheKeyPointsofManagementandControlintheConstructionStageof
SewageDisposalPipelineProject
朱建勇
(厦门百城建设投资有限公司,福建厦门361000)
ZHUJian-yong
(XiamenBaichengConstructionInvestmentCo.Ltd.,Xiamen361000,China)
【摘要】
随着我国经济和社会的不断发展,环保问题愈来愈受到人们的重视,海洋生态环境的重要性显得尤为突出。污水排海
管项目施工周期短,施工阶段项目管控须提前谋划、加强沟通。基于此,结合集美排海管管控经验从代建角度着重对施工阶段管控
要点进行简单的介绍。
【】
AbstractWiththecontinuousdevelopmentofourcountryseconomyandsociety,environmentalprotectionhasbeenpaidmoreand
moreattention,andtheimportanceofmarineecologicalenvironmentisparticularlyprominent.Theconstructionperiodofthesewage
disposalpipelineprojectisshort,andtheprojectmanagementandcontrolintheconstructionphasemustbeplannedinadvanceand
communicationmustbestrengthened.Basedonthis,combinedwithJimeismanagementandcontrolexperienceofseaoutfall,thekey
pointsofmanagementandcontrolintheconstructionphasearebrieflyintroducedfromtheperspectiveofagentconstruction.
【关键词】排海管;提前谋划;节点工期;项目管理
【】seaoutfall;planaheadoftime;nodeduration;projectmanagement
Keywords
【中图分类号】TU823.5【文献标志码】B【文章编号】1007-9467(2020)03-0280-03
【DOI】10.13616/j.cnki.gcjsysj.2020.03.105
5
1引言模为1.8×10t/d的集美污水处理厂尾水排海管及配套设施,将
集美污水处理厂处理达标后的尾水,离岸排至同安湾凤林临
为贯彻落实党中央、国务院关于建立和实施国家海洋督